Over a Third of EU Blast Furnace Capacity Hits 20 Years by 2030
Blast furnaces are relined every 15–25 years. Each reline costs from tens of millions to more than €200m, and it commits the owner to coal-based ironmaking for another campaign. Our furnace-by-furnace register shows how much EU capacity reaches that point before 2030 – and how little of it has a firm closure date.
Health warning: read these figures as campaign ages, not closure forecasts.
- Most of the 27.3 Mt/yr comes from an assumed 20-year campaign counted from each furnace's last full reline. A furnace past that age can keep running, be relined again, or close – the register shows when the decision falls due, not what the owner will decide.
- Only 0.8 Mt/yr has a committed closure. The rest rests on company plans that are conditional (for example on hydrogen supply or state funding) or on our campaign-age calculation.
- 7 active furnaces (11.4 Mt/yr) have no public full-reline date, so the 2030 figure is a minimum.
- Reline histories are often not published. Where a source is a database only (grade C), we say so; excluding those rows gives 26.5 Mt/yr.
- Compiled from public sources as of November 2026. Corrections from operators are welcome and will be dated.
Key Findings
- The age wall is close. 27.3 Mt/yr of the EU's 77.4 Mt/yr of active blast furnace capacity reaches or passes a 20-year campaign by 2030. A further decision exposure of 33.1 Mt/yr falls due by 2028, allowing about four years to plan, finance and build a reline or a replacement.
- Few closures are committed. Only voestalpine's Linz BF 5 (0.84 Mt/yr, replaced by an electric arc furnace (EAF) in 2027) has a definite date. Tata Steel IJmuiden BF 7, SSAB Luleå and thyssenkrupp Hamborn 8 all have planned end dates, but each depends on a replacement plant that has slipped or still needs funding or hydrogen.
- Replacement plans are stalling. ArcelorMittal cancelled its direct reduced iron (DRI) and EAF projects at Bremen and Eisenhüttenstadt in June 2025, and its Gent DRI project is on hold. thyssenkrupp's Duisburg DRI plant is now expected in 2029.
- Several furnaces are already past 20 years. ArcelorMittal Dunkirk BF 4 (3.6 Mt/yr) was last fully relined in 2001; its 2025 overhaul was major maintenance, not a reline. Tata IJmuiden BF 7, whose campaign dates from 1992 (with a 2006 reline of unconfirmed scope), is due to be replaced by 2030 under Tata's plans.
- Closures are already under way. At least 14 Mt/yr has closed or been mothballed since 2022, including HKM BF A (September 2026), SSAB Oxelösund (October 2026) and thyssenkrupp Hamborn 9 – and the shutdown of all blast furnaces at Taranto in November 2026, whose capacity is not included in that total.
When EU Blast Furnaces Reach a 20-Year Campaign
Active furnaces (operating or temporarily idled), grouped by the year their campaign ends: a committed closure where one exists, otherwise a company-stated horizon, otherwise last full reline plus 20 years.
| Campaign end | Furnaces | Capacity (Mt/yr) | Cumulative to 2030 (Mt/yr) |
|---|---|---|---|
| Already beyond 20 years | 1 | 3.6 | 3.6 |
| 2027 | 2 | 3.3 | 6.9 |
| 2028 | 1 | 3.6 | 10.5 |
| 2029 | 3 | 5.4 | 16.0 |
| 2030 | 5 | 11.4 | 27.3 |
| 2031–2035 | 7 | 17.2 | – |
| After 2035 | 11 | 21.5 | – |
| No date found | 7 | 11.4 | – |
| Total active | 37 | 77.4 | – |
Source: MCI research from company releases, trade press and Global Energy Monitor. Capacity is nominal hot metal; furnaces without a published capacity are counted but add nothing to the totals. Data as of November 2026.
Active Blast Furnaces in the EU-27
Sorted by campaign end year. Click a column heading to re-sort. Grade A = company or technical source; B = trade press; C = database only.
| Country | Owner | Plant | Furnace | Capacity (Mt/yr) | Status | Last full reline | End year | Basis | Grade | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| France | ArcelorMittal | Dunkirk | BF 4 | 3.6 | Operating | 2001 | 2021 | Beyond assumed campaign | A | La Gazette |
| Austria | voestalpine | Linz | BF 5 | 0.84 | Operating | 2023 | 2027 | Committed | A | voestalpine |
| France | ArcelorMittal | Fos-sur-Mer | BF 1 | 2.5 | Operating | 2007 | 2027 | Expected | A | GMK Center |
| Germany | thyssenkrupp Steel | Duisburg-Schwelgern | BF Schwelgern 1 | 3.6 | Operating | 2008 | 2028 | Expected | A | thyssenkrupp |
| Austria | voestalpine | Leoben-Donawitz | BF 4 | 0.82 | Operating | 2016 | 2029 | Expected | C | Global Energy Monitor |
| Germany | thyssenkrupp Steel | Duisburg-Hamborn | BF 8 | 2.0 | Operating | 2007 | 2029 | Expected | A | thyssenkrupp |
| Sweden | SSAB | Luleå | BF 3 | 2.6 | Operating | 2015 | 2029 | Expected | A | SSAB |
| Austria | voestalpine | Leoben-Donawitz | BF 1 | 0.82 | Operating | – | 2030 | Expected | A | voestalpine |
| France | ArcelorMittal | Dunkirk | BF 3 | 1.8 | Operating | 2023 | 2030 | Expected | A | Argus |
| Germany | ROGESA (Dillinger / Saarstahl) | Dillingen/Saar | BF 5 | 2.6 | Operating | 2010 | 2030 | Expected | B | SMS group |
| Netherlands | Tata Steel Nederland | IJmuiden | BF 7 | 4.0 | Operating | 1992 | 2030 | Expected | A | Danieli Corus |
| Poland | ArcelorMittal Poland | Dąbrowa Górnicza | BF 3 | 2.2 | Operating | – | 2030 | Expected | A | GMK Center |
| France | ArcelorMittal | Fos-sur-Mer | BF 2 | 2.5 | Operating | 2011 | 2031 | Expected | B | AFP |
| Austria | voestalpine | Linz | BF A | 3.3 | Operating | 2018 | 2032 | Expected | A | voestalpine |
| Germany | Salzgitter Flachstahl | Salzgitter | BF A | 2.0 | Operating | 2024 | 2033 | Expected | A | Salzgitter |
| Germany | Salzgitter Flachstahl | Salzgitter | BF B | 2.2 | Operating | 2016 | 2033 | Expected | A | Salzgitter |
| Germany | Salzgitter Flachstahl | Salzgitter | BF C | 0.69 | Idled | 2008 | 2033 | Expected | B | GMK Center |
| Germany | thyssenkrupp Steel | Duisburg-Schwelgern | BF Schwelgern 2 | 4.0 | Operating | 2014 | 2034 | Expected | A | thyssenkrupp |
| Netherlands | Tata Steel Nederland | IJmuiden | BF 6 | 2.5 | Operating | 2024 | 2035 | Expected | A | Tata Steel |
| Germany | ROGESA (Dillinger / Saarstahl) | Dillingen/Saar | BF 4 | 2.2 | Operating | 2016 | 2036 | Expected | A | SMS group |
| Germany | ArcelorMittal | Eisenhüttenstadt | BF 5A | 1.8 | Operating | 2016 | 2036 | Expected | A | ArcelorMittal |
| Germany | ArcelorMittal | Bremen | BF 2 | 2.5 | Operating | 2017 | 2037 | Expected | B | SteelOrbis |
| Slovakia | U.S. Steel Košice (Nippon Steel) | Košice | BF 2 | 1.7 | Idled | 2017 | 2037 | Potential | C | Eurometal |
| Poland | ArcelorMittal Poland | Dąbrowa Górnicza | BF 2 | 2.3 | Operating | – | 2038 | Expected | A | money.pl |
| Belgium | ArcelorMittal | Gent | BF B | 2.3 | Operating | 2021 | 2041 | Expected | A | ArcelorMittal |
| Czech Republic | Třinecké železárny | Třinec | BF 6 | 1.1 | Operating | 2021 | 2041 | Expected | B | Paul Wurth |
| Belgium | ArcelorMittal | Gent | BF A | 2.7 | Operating | 2023 | 2043 | Expected | A | VRT |
| Finland | SSAB | Raahe | BF 1 | 1.3 | Operating | 2023 | 2043 | Potential | C | SSAB |
| Austria | voestalpine | Linz | BF 6 | 0.85 | Operating | 2024 | 2044 | Expected | A | voestalpine |
| Germany | Salzgitter (HKM) | Duisburg-Huckingen | BF B | 2.7 | Operating | 2026 | 2046 | Expected | B | SteelOrbis |
| Czech Republic | Třinecké železárny | Třinec | BF 4 | 1.2 | Operating | – | – | No date found | A | Třinecké železárny |
| Finland | SSAB | Raahe | BF 2 | 1.3 | Operating | – | – | No date found | B | SSAB |
| Germany | ArcelorMittal | Bremen | BF 3 | 1.4 | Operating | – | – | No date found | B | Eurometal |
| Slovakia | U.S. Steel Košice (Nippon Steel) | Košice | BF 1 | 1.3 | Operating | – | – | No date found | A | Eurometal |
| Slovakia | U.S. Steel Košice (Nippon Steel) | Košice | BF 3 | 1.5 | Operating | – | – | No date found | A | Eurometal |
| Spain | ArcelorMittal | Gijón | BF A | 2.4 | Operating | – | – | No date found | A | GMK Center |
| Spain | ArcelorMittal | Gijón | BF B | 2.4 | Operating | – | – | No date found | B | Eurometal |
Source: MCI research; each row links to its main source. "Committed" = definite company or legal closure. "Expected" = company plan or horizon, or confirmed full reline + 20 years. "Beyond assumed campaign" = last full reline more than 20 years ago, with no later end date. "Potential" = reline date found but full-reline scope not confirmed; not counted in the headline totals. "No date found" = no public full-reline date. – = not published. Data as of November 2026.
Closed and Mothballed Blast Furnaces Since 2022
| Country | Owner | Plant | Furnace | Capacity (Mt/yr) | Status | Since | Source |
|---|---|---|---|---|---|---|---|
| Czech Republic | Nová Huť (ex-Liberty Ostrava) | Ostrava | BF 1–4 (site) | 4.0 | Closed | October 2023 | GMK Center |
| France | ArcelorMittal | Dunkirk | BF 2 | 1.4 | Closed | December 2022 | SteelRadar |
| Germany | thyssenkrupp Steel | Duisburg-Hamborn | BF 9 | 1.7 | Closed | October 2025 | Eurometal |
| Germany | Salzgitter (HKM) | Duisburg-Huckingen | BF A | 2.5 | Closed | 19 September 2026 | ingenieur.de |
| Hungary | Dunaferr (in liquidation) | Dunaújváros | BF 1–2 (site) | 1.2 | Closed | October 2025 | Global Energy Monitor |
| Italy | Acciaierie d'Italia (extraordinary administration) | Taranto | AFO 1 | – | Closed | 6 November 2026 | GMK Center |
| Italy | Acciaierie d'Italia (extraordinary administration) | Taranto | AFO 2 | – | Closed | 6 November 2026 | GMK Center |
| Italy | Acciaierie d'Italia (extraordinary administration) | Taranto | AFO 4 | – | Closed | 6 November 2026 | GMK Center |
| Italy | Acciaierie d'Italia (extraordinary administration) | Taranto | AFO 5 | – | Closed | 2015 | Il Post |
| Romania | Liberty Galați | Galați | BF 5 | 2.1 | Mothballed | May 2024 | GMK Center |
| Sweden | SSAB | Oxelösund | BF 4 | 1.0 | Closed | 19 October 2026 | SMM |
| Sweden | SSAB | Oxelösund | BF 2 | 0.55 | Closed | 2026 | SSAB |
Source: MCI research. Taranto AFO 5 has been idle since 2015 and is listed for completeness. Ostrava capacity is the site figure as reported and may refer to crude steel rather than hot metal. Data as of November 2026.
Download the full register, including later interventions, plan details and every source, as an Excel workbook (xlsx).
Methodology
Campaign. A campaign runs from one full reline – renewal of the main refractory lining – to the next. Hearth repairs, partial relines, stave and cooling replacements and life-extension works are recorded in the register but do not restart the campaign clock.
Campaign end. We use, in order: a committed closure date; a company-stated horizon or planned end (for example "a further 15 years of operation"); otherwise the last full reline plus 20 years. The downloadable workbook lets you change the cut-off year.
Decision year. Campaign end minus four years, the typical time to plan, finance and order a reline or a replacement.
Capacity and scope. Nominal hot-metal capacity of each furnace, in Mt/yr. Active capacity covers furnaces operating or temporarily idled; mothballed and closed furnaces are excluded. EU-27 blast furnaces at steelworks only; foundry and merchant-iron blast furnaces are excluded.
Evidence. Each row carries a source grade: A for company or technical sources, B for credible trade press, C where the only source is a database such as Global Energy Monitor. Where a reline date is known but its scope is not, the furnace is shown as "Potential" and left out of the headline totals. We record the absence of a public source as such rather than estimating it.
How to Cite This Page
Metals Consulting International (2026) 'EU Blast Furnace Tracker: Reline-or-Replace Decisions', SteelOnTheNet. Available at: https://www.steelonthenet.com/resources/capacity/eu-blast-furnace-tracker.html (Accessed: 22 November 2026).
Related: green steel promises, green steel essentials, steel capital investment and our plant capacity database.