EU Blast Furnace Tracker | Reline-or-Replace Decisions

Over a Third of EU Blast Furnace Capacity Hits 20 Years by 2030

Blast furnaces are relined every 15–25 years. Each reline costs from tens of millions to more than €200m, and it commits the owner to coal-based ironmaking for another campaign. Our furnace-by-furnace register shows how much EU capacity reaches that point before 2030 – and how little of it has a firm closure date.

27.3 Mt/yr
Reaches or exceeds a 20-year campaign by 2030 – 35% of the 77.4 Mt/yr active fleet
0.8 Mt/yr
Has a committed closure date by 2030
33.1 Mt/yr
Faces a reline-or-replace decision by 2028

Health warning: read these figures as campaign ages, not closure forecasts.

  • Most of the 27.3 Mt/yr comes from an assumed 20-year campaign counted from each furnace's last full reline. A furnace past that age can keep running, be relined again, or close – the register shows when the decision falls due, not what the owner will decide.
  • Only 0.8 Mt/yr has a committed closure. The rest rests on company plans that are conditional (for example on hydrogen supply or state funding) or on our campaign-age calculation.
  • 7 active furnaces (11.4 Mt/yr) have no public full-reline date, so the 2030 figure is a minimum.
  • Reline histories are often not published. Where a source is a database only (grade C), we say so; excluding those rows gives 26.5 Mt/yr.
  • Compiled from public sources as of November 2026. Corrections from operators are welcome and will be dated.

Key Findings

  • The age wall is close. 27.3 Mt/yr of the EU's 77.4 Mt/yr of active blast furnace capacity reaches or passes a 20-year campaign by 2030. A further decision exposure of 33.1 Mt/yr falls due by 2028, allowing about four years to plan, finance and build a reline or a replacement.
  • Few closures are committed. Only voestalpine's Linz BF 5 (0.84 Mt/yr, replaced by an electric arc furnace (EAF) in 2027) has a definite date. Tata Steel IJmuiden BF 7, SSAB Luleå and thyssenkrupp Hamborn 8 all have planned end dates, but each depends on a replacement plant that has slipped or still needs funding or hydrogen.
  • Replacement plans are stalling. ArcelorMittal cancelled its direct reduced iron (DRI) and EAF projects at Bremen and Eisenhüttenstadt in June 2025, and its Gent DRI project is on hold. thyssenkrupp's Duisburg DRI plant is now expected in 2029.
  • Several furnaces are already past 20 years. ArcelorMittal Dunkirk BF 4 (3.6 Mt/yr) was last fully relined in 2001; its 2025 overhaul was major maintenance, not a reline. Tata IJmuiden BF 7, whose campaign dates from 1992 (with a 2006 reline of unconfirmed scope), is due to be replaced by 2030 under Tata's plans.
  • Closures are already under way. At least 14 Mt/yr has closed or been mothballed since 2022, including HKM BF A (September 2026), SSAB Oxelösund (October 2026) and thyssenkrupp Hamborn 9 – and the shutdown of all blast furnaces at Taranto in November 2026, whose capacity is not included in that total.

When EU Blast Furnaces Reach a 20-Year Campaign

Active furnaces (operating or temporarily idled), grouped by the year their campaign ends: a committed closure where one exists, otherwise a company-stated horizon, otherwise last full reline plus 20 years.

EU-27 Active Blast Furnace Capacity by Campaign End Year
Campaign endFurnacesCapacity (Mt/yr)Cumulative to 2030 (Mt/yr)
Already beyond 20 years13.63.6
202723.36.9
202813.610.5
202935.416.0
2030511.427.3
2031–2035717.2–
After 20351121.5–
No date found711.4–
Total active3777.4–

Source: MCI research from company releases, trade press and Global Energy Monitor. Capacity is nominal hot metal; furnaces without a published capacity are counted but add nothing to the totals. Data as of November 2026.

Active Blast Furnaces in the EU-27

Sorted by campaign end year. Click a column heading to re-sort. Grade A = company or technical source; B = trade press; C = database only.

EU-27 Blast Furnaces in Operation or Temporarily Idled, November 2026
CountryOwnerPlantFurnaceCapacity (Mt/yr)StatusLast full relineEnd yearBasisGradeSource
FranceArcelorMittalDunkirkBF 43.6Operating20012021Beyond assumed campaignALa Gazette
AustriavoestalpineLinzBF 50.84Operating20232027CommittedAvoestalpine
FranceArcelorMittalFos-sur-MerBF 12.5Operating20072027ExpectedAGMK Center
Germanythyssenkrupp SteelDuisburg-SchwelgernBF Schwelgern 13.6Operating20082028ExpectedAthyssenkrupp
AustriavoestalpineLeoben-DonawitzBF 40.82Operating20162029ExpectedCGlobal Energy Monitor
Germanythyssenkrupp SteelDuisburg-HambornBF 82.0Operating20072029ExpectedAthyssenkrupp
SwedenSSABLuleåBF 32.6Operating20152029ExpectedASSAB
AustriavoestalpineLeoben-DonawitzBF 10.82Operating–2030ExpectedAvoestalpine
FranceArcelorMittalDunkirkBF 31.8Operating20232030ExpectedAArgus
GermanyROGESA (Dillinger / Saarstahl)Dillingen/SaarBF 52.6Operating20102030ExpectedBSMS group
NetherlandsTata Steel NederlandIJmuidenBF 74.0Operating19922030ExpectedADanieli Corus
PolandArcelorMittal PolandDąbrowa GórniczaBF 32.2Operating–2030ExpectedAGMK Center
FranceArcelorMittalFos-sur-MerBF 22.5Operating20112031ExpectedBAFP
AustriavoestalpineLinzBF A3.3Operating20182032ExpectedAvoestalpine
GermanySalzgitter FlachstahlSalzgitterBF A2.0Operating20242033ExpectedASalzgitter
GermanySalzgitter FlachstahlSalzgitterBF B2.2Operating20162033ExpectedASalzgitter
GermanySalzgitter FlachstahlSalzgitterBF C0.69Idled20082033ExpectedBGMK Center
Germanythyssenkrupp SteelDuisburg-SchwelgernBF Schwelgern 24.0Operating20142034ExpectedAthyssenkrupp
NetherlandsTata Steel NederlandIJmuidenBF 62.5Operating20242035ExpectedATata Steel
GermanyROGESA (Dillinger / Saarstahl)Dillingen/SaarBF 42.2Operating20162036ExpectedASMS group
GermanyArcelorMittalEisenhüttenstadtBF 5A1.8Operating20162036ExpectedAArcelorMittal
GermanyArcelorMittalBremenBF 22.5Operating20172037ExpectedBSteelOrbis
SlovakiaU.S. Steel Košice (Nippon Steel)KošiceBF 21.7Idled20172037PotentialCEurometal
PolandArcelorMittal PolandDąbrowa GórniczaBF 22.3Operating–2038ExpectedAmoney.pl
BelgiumArcelorMittalGentBF B2.3Operating20212041ExpectedAArcelorMittal
Czech RepublicTřinecké železárnyTřinecBF 61.1Operating20212041ExpectedBPaul Wurth
BelgiumArcelorMittalGentBF A2.7Operating20232043ExpectedAVRT
FinlandSSABRaaheBF 11.3Operating20232043PotentialCSSAB
AustriavoestalpineLinzBF 60.85Operating20242044ExpectedAvoestalpine
GermanySalzgitter (HKM)Duisburg-HuckingenBF B2.7Operating20262046ExpectedBSteelOrbis
Czech RepublicTřinecké železárnyTřinecBF 41.2Operating––No date foundATřinecké železárny
FinlandSSABRaaheBF 21.3Operating––No date foundBSSAB
GermanyArcelorMittalBremenBF 31.4Operating––No date foundBEurometal
SlovakiaU.S. Steel Košice (Nippon Steel)KošiceBF 11.3Operating––No date foundAEurometal
SlovakiaU.S. Steel Košice (Nippon Steel)KošiceBF 31.5Operating––No date foundAEurometal
SpainArcelorMittalGijónBF A2.4Operating––No date foundAGMK Center
SpainArcelorMittalGijónBF B2.4Operating––No date foundBEurometal

Source: MCI research; each row links to its main source. "Committed" = definite company or legal closure. "Expected" = company plan or horizon, or confirmed full reline + 20 years. "Beyond assumed campaign" = last full reline more than 20 years ago, with no later end date. "Potential" = reline date found but full-reline scope not confirmed; not counted in the headline totals. "No date found" = no public full-reline date. – = not published. Data as of November 2026.

Closed and Mothballed Blast Furnaces Since 2022

EU-27 Blast Furnaces Closed or Mothballed
CountryOwnerPlantFurnaceCapacity (Mt/yr)StatusSinceSource
Czech RepublicNová Huť (ex-Liberty Ostrava)OstravaBF 1–4 (site)4.0ClosedOctober 2023GMK Center
FranceArcelorMittalDunkirkBF 21.4ClosedDecember 2022SteelRadar
Germanythyssenkrupp SteelDuisburg-HambornBF 91.7ClosedOctober 2025Eurometal
GermanySalzgitter (HKM)Duisburg-HuckingenBF A2.5Closed19 September 2026ingenieur.de
HungaryDunaferr (in liquidation)DunaújvárosBF 1–2 (site)1.2ClosedOctober 2025Global Energy Monitor
ItalyAcciaierie d'Italia (extraordinary administration)TarantoAFO 1–Closed6 November 2026GMK Center
ItalyAcciaierie d'Italia (extraordinary administration)TarantoAFO 2–Closed6 November 2026GMK Center
ItalyAcciaierie d'Italia (extraordinary administration)TarantoAFO 4–Closed6 November 2026GMK Center
ItalyAcciaierie d'Italia (extraordinary administration)TarantoAFO 5–Closed2015Il Post
RomaniaLiberty GalațiGalațiBF 52.1MothballedMay 2024GMK Center
SwedenSSABOxelösundBF 41.0Closed19 October 2026SMM
SwedenSSABOxelösundBF 20.55Closed2026SSAB

Source: MCI research. Taranto AFO 5 has been idle since 2015 and is listed for completeness. Ostrava capacity is the site figure as reported and may refer to crude steel rather than hot metal. Data as of November 2026.

Download the full register, including later interventions, plan details and every source, as an Excel workbook (xlsx).

Methodology

Campaign. A campaign runs from one full reline – renewal of the main refractory lining – to the next. Hearth repairs, partial relines, stave and cooling replacements and life-extension works are recorded in the register but do not restart the campaign clock.

Campaign end. We use, in order: a committed closure date; a company-stated horizon or planned end (for example "a further 15 years of operation"); otherwise the last full reline plus 20 years. The downloadable workbook lets you change the cut-off year.

Decision year. Campaign end minus four years, the typical time to plan, finance and order a reline or a replacement.

Capacity and scope. Nominal hot-metal capacity of each furnace, in Mt/yr. Active capacity covers furnaces operating or temporarily idled; mothballed and closed furnaces are excluded. EU-27 blast furnaces at steelworks only; foundry and merchant-iron blast furnaces are excluded.

Evidence. Each row carries a source grade: A for company or technical sources, B for credible trade press, C where the only source is a database such as Global Energy Monitor. Where a reline date is known but its scope is not, the furnace is shown as "Potential" and left out of the headline totals. We record the absence of a public source as such rather than estimating it.

How to Cite This Page

Metals Consulting International (2026) 'EU Blast Furnace Tracker: Reline-or-Replace Decisions', SteelOnTheNet. Available at: https://www.steelonthenet.com/resources/capacity/eu-blast-furnace-tracker.html (Accessed: 22 November 2026).

Related: green steel promises, green steel essentials, steel capital investment and our plant capacity database.