Skip to content

Japan Coke Oven Tracker | Battery Age, Rebuilds and Closures

Rebuilt to Run Past 2050

A coke oven battery is a brick structure that runs hot for 40 years or more, and once cooled it rarely restarts. Recent rebuilds have cost ¥13–50bn each, and each one commits the owner to coal-based ironmaking for decades. Our battery-by-battery register shows two fleets side by side in Japan: batteries from the 1960s and 1970s that have never been rebuilt, and a wave of rebuilds since 2011 whose design life reaches well beyond 2050. It is a companion to our EU blast furnace tracker, which asks the same reline-or-replace question of Europe's furnaces.

36%
Of confirmed working coke ovens are in batteries built 1964–1980 and never rebuilt (894 of 2,516 ovens)
7.6 Mt/yr
Built or rebuilt since 2011 – on a 40-year life, still operable after 2050
723 ovens
Closed or scheduled to close between 2021 and 2027, where oven counts are published

Health Warning: Read These Figures as Asset Ages, Not Closure Forecasts

  • Nippon Steel does not publish a battery list. Nine of its batteries (737 ovens) have no public status update since 2015 and are shown separately; they are excluded from the 36% and 2,516-oven figures.
  • The 7.6 million tonnes a year (Mt/yr) counts only batteries with a published capacity. It rises to 9.1 Mt/yr if the Kimitsu No. 3 and Oita No. 2 rebuilds, due in FY2025–26 but not yet confirmed as commissioned, are included.
  • A 40-year life is a convention, not a guarantee: Japanese batteries often run 50 years with hot repairs. "Never rebuilt" means no public record of a full or pad-up rebuild; hot repairs are not counted.
  • Published capacity is missing for most older batteries, so the age figures are given in ovens, not tonnes.
  • Compiled from public sources as of November 2026. Corrections from operators are welcome and will be dated.

Key Findings

  • The old fleet is still large. Of the 2,516 ovens we can confirm as working, 894 are in batteries started between 1964 and 1980 with no public record of a rebuild, at Yawata, Chiba, Kurashiki, Fukuyama and Kakogawa. The oldest, Yawata (Tobata) No. 4, dates from 1965. Kashima No. 1 A–D (1971) would add to the total, but its oven count is not published.
  • The rebuilds run past 2050. Since 2011 Nippon Steel, JFE and Nippon Coke & Engineering have completed 16 new or rebuilt batteries and one rebuilt half-battery, with 7.6 Mt/yr of published capacity between them, from Nagoya No. 5 (2013) to JFE's stamp-charged Fukuyama No. 6A, which started on 31 August 2026 at a cost of about ¥45bn. On a 40-year life, every one of them is still operable after 2050.
  • Closures are accelerating. Kure closed in 2021 and JFE Keihin in 2023. Kashima No. 2 A–D was scheduled to close at the end of FY2024, and Fukuyama No. 4, Kurashiki 1B and Nippon Coke 1B and 2B in FY2025–26. Mitsubishi Chemical will stop coke production at Kagawa in the second half of FY2027.
  • The coke clock is now tied to the EAF switch. Nippon Steel's Yawata coke works will close when its new EAF replaces the blast furnace (EAF output from the second half of FY2029). JFE will stop Fukuyama No. 4 blast furnace in FY2027 and Kurashiki No. 4 coke battery in FY2027, ahead of the Kurashiki EAF in FY2028. Kobe Steel's Kakogawa batteries (1970–1973) have no closure date.
  • Stranded-asset risk sits in the new batteries, not the old ones. A 1970s battery that closes with its blast furnace is written off. A battery rebuilt in 2017–2026 for ¥30–50bn that closes in the 2030s is not. Europe faces the same choice with its blast furnaces: over a third of EU capacity reaches a 20-year campaign by 2030 (see the EU tracker).

Japan's Working Coke Ovens by Age of Battery

Batteries in operation or scheduled to close, grouped by their latest full or pad-up rebuild, or by original start-up if never rebuilt.

Japanese Coke Ovens by Date of Latest Build or Rebuild, November 2026
Latest Build or RebuildBatteries or HalvesOvensShare of Confirmed Ovens (%)Published Capacity (Mt/yr)
2011–2026[a][b]191,199489.1
2001–20105273111.9
1964–1980, never rebuilt[b]1189436–
Start date not published115061.5
Total confirmed[c]362,516100–
Status not confirmed since 20159737––

Source: MCI research from company releases, technical reports and trade press. Shares are rounded. "Published capacity" sums only batteries with a published figure; "–" means too few are published to give a meaningful total. Data as of November 2026.

  1. Includes Kimitsu No. 3 (0.7 Mt/yr) and Oita No. 2 (0.8 Mt/yr), whose rebuilds are not yet confirmed as commissioned; without them the figure is 7.6 Mt/yr. Oven counts for those two are pre-rebuild.
  2. Kurashiki No. 6 is split between rows and counted in both: its 43-oven 6B half was rebuilt in 2011, the other half dates from 1980.
  3. Kashima No. 1 A–D, 1E and 2E and Oita No. 5 are counted as batteries but their oven counts are not published.

Coke Oven Batteries in Japan

Click a column heading to re-sort. Grade A = company, government or technical source; B = trade press; C = database or secondary compilation.

Japanese Coke Oven Batteries in Operation or Status Unconfirmed, November 2026
OwnerWorksBatteryOvensCapacity (Mt/yr)Original Start-UpLatest RebuildStatusGradeSource
Nippon SteelNagoyaNo. 175–1964–Restarted October 2015 after 2014 explosion; current status not publishedANippon Steel
Nippon SteelNagoyaNo. 1A25––2005Historical configurationANippon Steel
Nippon SteelNagoyaNo. 2110–1967–Restarted September 2014; current status not publishedANippon Steel
Nippon SteelNagoyaNo. 3840.8019682021Confirmed operatingANippon Steel
Nippon SteelNagoyaNo. 4100–1969–Restarted September 2014; current status not publishedANippon Steel
Nippon SteelNagoyaNo. 5 (SCOPE21)641.002013–Confirmed operatingANippon Steel
Nippon SteelYawata (Tobata)No. 490–1965–Coke works to close with EAF switch (BF to stop about September 2030); battery dates not statedANippon Steel
Nippon SteelYawata (Tobata)No. 5110–1970–Coke works to close with EAF switch (BF to stop about September 2030); battery dates not statedANippon Steel
Nippon SteelKimitsuNo. 190–1968–Historical configurationANippon Steel
Nippon SteelKimitsuNo. 295–1969–Historical configurationANippon Steel
Nippon SteelKimitsuNo. 31000.701969Due H1 FY2026Rebuild; start-up not confirmedANippon Steel
Nippon SteelKimitsuNo. 4920.9019712017Confirmed operatingANippon Steel
Nippon SteelKimitsuNo. 5920.9019732019Confirmed operatingANippon Steel
Nippon SteelKashimaNo. 1 A–D––1971–Operating (works-level confirmation)ANippon Steel
Nippon SteelKashimaNo. 1E––2011–Confirmed operatingANippon Steel
Nippon SteelKashimaNo. 1F330.342016–Confirmed operatingANippon Steel
Nippon SteelKashimaNo. 2E–0.582018–Confirmed operating (new battery added; not a rebuild)ANippon Steel
Nippon SteelOitaNo. 178–1972–Historical configurationANippon Steel
Nippon SteelOitaNo. 2780.801972FY2025 (reported)Reported completed FY2025; start-up date and oven count not confirmedBJapan Metal Daily
Nippon SteelOitaNo. 382–1976–Historical configurationANippon Steel
Nippon SteelOitaNo. 482–1976–Historical configurationANippon Steel
Nippon SteelOitaNo. 5 (SCOPE21)–1.002008–Confirmed operatingANippon Steel
Hokkai Steel (Nippon Steel)MuroranNo. 5 West450.2819692019Confirmed operatingANippon Steel
Hokkai Steel (Nippon Steel)MuroranNo. 5 East450.2819692011OperatingANippon Steel
Hokkai Steel (Nippon Steel)MuroranNo. 642–19652007 (pad-up)OperatingANippon Steel
Nippon SteelWakayamaNew No. 1130–[a]2009–Current status not publishedAMETI
JFE SteelChibaNo. 6 (A, B)102–19732016 (pad-up)OperatingAJFE Steel
JFE SteelChibaNo. 766–1980–OperatingAJFE Steel
JFE SteelKurashikiNo. 1A[b]39–19672013 (pad-up)OperatingAJFE Steel
JFE SteelKurashikiNo. 2 (A, B)860.72–2017 (pad-up)OperatingAPaul Wurth IHI
JFE SteelKurashikiNo. 3 (A, B)86––2016 (pad-up)OperatingAJFE Steel
JFE SteelKurashikiNo. 4 (A, B)86–1971–Scheduled closure FY2027AJFE Holdings
JFE SteelKurashikiNo. 586–1973–OperatingAJFE Steel
JFE SteelKurashikiNo. 686–19802011 (6B half only)OperatingAJFE Steel
JFE SteelFukuyamaNo. 3 (A, B)1040.72–2019 / 2021 (pad-up)Confirmed operatingAJFE Steel
JFE SteelFukuyamaNo. 5 (A–C)1651.12[c]1973–Confirmed operatingAJFE Steel
JFE SteelFukuyamaNo. 5D550.402006–Confirmed operatingAJFE Technical Report
JFE SteelFukuyamaNo. 6A (stamp-charged)520.422026–Confirmed operating from 31 August 2026AJFE Steel
Kansai Coke (100% Kobe Steel)KakogawaNo. 1 and No. 2120–1970–Operating in 2019; current status not publishedAKobe Steel
Kansai Coke (100% Kobe Steel)KakogawaNo. 364–1972–Operating in 2019; current status not publishedAKobe Steel
Kansai Coke (100% Kobe Steel)KakogawaNo. 464–1973–Operating in 2019; current status not publishedAKobe Steel
Nippon Coke & EngineeringKitakyushu1A460.4519732006Confirmed operating (restarted January 2026 after conveyor fire)ANippon Coke
Nippon Coke & EngineeringKitakyushu2A540.6519802024Confirmed operatingANippon Coke
Mitsubishi ChemicalKagawa (Sakaide)Site (150 ovens)1501.50––Scheduled closure H2 FY2027AMitsubishi Chemical

Source: MCI research from company releases, technical reports and trade press. "Latest rebuild" = full rebuild or pad-up (new battery body on the existing foundation); hot repairs are excluded. Grade A = company, government or technical source; B = trade press; C = database or secondary compilation. "Historical configuration" = start date and oven count from an older technical source, with no later public statement of status; these rows are excluded from headline active-capacity totals. "Scheduled closure" = published plan; final operating date not yet confirmed. FY = Japanese fiscal year (April–March). – = not published. Data as of November 2026.

  1. Rated at 2,800 t/d (METI); no annual capacity is published.
  2. Kurashiki No. 1 is shown as two 39-oven halves because JFE reports 1A and 1B separately; 1B is in the closures table.
  3. The 1.52 Mt/yr battery total less the 0.40 Mt/yr 5D battery.

Coke Oven Batteries Closed or Scheduled to Close Since 2018

Japanese Coke Oven Batteries Closed or Scheduled to Close Since 2018
OwnerWorksBatteryOvensCapacity (Mt/yr)Original Start-UpStatusSinceGradeSource
Nippon SteelKureAll batteries (site)[a]–––Confirmed closedSeptember 2021AKure City
Nippon SteelWakayamaNo. 5–––Closed with BF 1; date not publishedSeptember 2021ANippon Steel
Nippon SteelWakayamaNo. 4–––Scheduled closure (delayed from H1 FY2022)End FY2024AISIJ International
Nippon SteelKashimaNo. 2 A–D–––Scheduled closure with BF 3; stop date not publishedEnd FY2024ANippon Steel
JFE SteelChibaNo. 5–––Confirmed closedDecember 2018AJFE Steel
JFE SteelKeihinNo. 1–––Confirmed closedSeptember 2023AJFE Steel
JFE SteelKeihinNo. 2–––Confirmed closedSeptember 2023AJFE Steel
JFE SteelKurashikiNo. 1B39–1967Scheduled closure; stop date not publishedFY2025[b]AJFE Holdings
JFE SteelFukuyamaNo. 4 (A–C)175–1971Reported suspended (brought forward from FY2026); stop date not publishedFY2025[b]AJFE Holdings
Nippon Coke & EngineeringKitakyushu1B460.451974Scheduled suspension; stop date not publishedFY2025[b]ANippon Coke
Nippon Coke & EngineeringKitakyushu2B540.451977Scheduled suspension; stop date not publishedH1 FY2026[b]ANippon Coke
Mitsubishi ChemicalKagawa (Sakaide)73 of 323 ovens[c]73––Confirmed closedMarch 2021AMitsubishi Chemical
Mitsubishi ChemicalKagawa (Sakaide)100 of 250 ovens100––Confirmed closedMarch 2025AMitsubishi Chemical

Source: MCI research. Data as of November 2026.

  1. Kure ironmaking, including coke, stopped at the end of September 2021 and the whole site closed in September 2023.
  2. Scheduled to stop within the fiscal period shown; the final stop date has not been published.
  3. Kagawa had 323 ovens before 2021.

Download the full register, with source links, age calculations and an adjustable design-life assumption, as an Excel workbook (xlsx).

Methodology

Battery. A block of ovens sharing one structure and heating system. Where a company reports halves separately (for example Kurashiki 1A and 1B), each half is listed as its own row.

Rebuild. A full rebuild or a pad-up, in which the battery is rebuilt above its existing concrete foundation. Both restart the age clock for the rebuilt structure. Hot repairs, end-flue repairs and partial relining are excluded. Where only half a battery was rebuilt, the older half keeps its original date.

Stranded capacity. Coke capacity, and the rebuild capital sunk in it, whose remaining design life runs beyond the date its demand disappears – when the blast furnace it feeds closes or converts to an EAF, or by Japan's 2050 net-zero target. Our steel stranded assets analysis sets Japan's rebuilt and closing batteries against EU blast furnace relines.

Design life. We use 40 years from the latest build or rebuild as the base case. Japanese practice often extends this to 50 years with hot repairs, so the "after 2050" figure is conservative on that basis.

Status. "Confirmed operating" requires a company or technical source dated 2019 or later. "Historical configuration" means a start date and oven count from an older technical source with no later public statement of status; these batteries are excluded from the headline figures. "Scheduled closure" means a published plan with no confirmed final operating date.

Capacity and scope. Published annual coke capacity in Mt/yr as stated by the operator; no figures are estimated. Coverage is blast-furnace coke at steelworks and merchant metallurgical coke plants. Works-level crude steel and finished-product capacity for the same sites is in our plant capacity database. Gas-works and foundry coke ovens are excluded.

Evidence. Every row links to its main source and carries a grade. The downloadable workbook lets you change the design-life assumption and the as-of year. We record the absence of a public source as such rather than estimating it.

How to Cite This Page

Metals Consulting International (2026) 'Japan Coke Oven Tracker: Battery Age, Rebuilds and Closures', SteelOnTheNet. Available at: https://www.steelonthenet.com/resources/capacity/japan-coke-battery-tracker.html (Accessed: 24 November 2026).

Related: steel stranded assets, EU blast furnace tracker, steel capacity reports and data, green steel promises, green steel essentials, steel capital investment and our plant capacity database.

Need Deeper Research on Coke and Ironmaking Assets?

152 projects in 48 countries since 2001

Free, confidential first conversation No obligation Reply within one working day