Steel Capex Projects 2025 | Capital Investment Database

Steel Industry Capex

ArchiveSteel Capex Projects 2025. This page records steel industry projects scheduled for commissioning in 2025, kept as a historical record. Compiled November 2024. Figures are as published and are not revised, so they reflect conditions at that time. For the latest figures, see Steel Capex Projects 2026.
2025 Steel Sector Capital Investments
CountryInvestorFacilityEquipmentCapacity (kt)Capex (US$m)
AustraliaRio Tinto / Baowu JVWestern RangeIron ore mine25,0002,000
BrazilValeMarabaBlast furnace250337
ChinaFujian TsingtuoFu'an CityStainless plate1,000280
ChinaPOSCOZhangjiagang WorksPlate mill [stainless]6045
Czech RepubLiberty SteelNová HuťEAF3,500351
GermanySalzgitterFlachstahlEAF1,900732
IndiaJupiter / TatravagonkaJV Railwheel FactoryRailway wheels80300
KoreaPOSCOGwangyangElectrical steel300804
MexicoTalleres y AcerosTyasaSBQ bar mill363250
RussiaEvrazZapsibEndless casting rolling2,500650
RussiaOMKVyksaDRI/EAF / CC1,8002,000
RussiaPrimorskyPrimorsky SteelHRC / LDP1,5002,200
Saudi ArabiaEssar GroupRas Al Khair Ind CityDRI/EAF / HRC / CRC4,0004,000
Saudi ArabiaJ.O. Steel HoldingsRas Al Khair Ind CityBillet mill1,800865
Saudi ArabiaSeAH Gulf SteelKing Salman CityStainless steel pipe mill20266
TurkeyAlter Iron & SteelAlter Energy ParkSolar power185.5
TurkeyBMS WireBMS Wire WorksWire drawing plant361
TurkeyEkincilerUncertainSolar power31.215.4
TurkeyIsik SteelUncertainSolar power6.194.57
TurkeyOyak / JFE SteelHekimhan locationPellet plant3,000750
TurkeyTosyalı HoldingsToscelikSlag processing1,2002.6
TurkeyTosyalı HoldingsToscelikSolar power13153.3
UkraineMetinvestIlyich SteelCRM / HDG / AlZn1,200800
USCMCNot specifiedMicro-mill453450
USNucorBerkeleyHDG453425
USNucorCalifornia Steel IndustriesHDG363370
USPacific SteelMojaveMicro-mill345350

Source: MCI research. Data as of November 2024.

Vale 'green' pig iron plant will use Tecnored technology.
Evraz ZSMK ESP line will produce 0.8–16 mm gauge hot rolled coil.
OMK plant in Vyksa will produce 2.5 Mt/yr of DRI, based on Energiron process.
Metinvest's Ilyich cold mill complex in Mariupol was not built: work stopped in 2022 and the city has been under Russian occupation since then.
Liberty Steel's EAF at Nová Huť (Ostrava) was not built after Liberty Ostrava's insolvency; since 1 October 2025 the plant, renamed Nová Huť, has been planning an EAF of about 1.5 Mt/yr (GMK Center; Eurometal).
Nucor HDG line in Berkeley will process coils up to 72 inches wide.
Pacific Steel micro-mill will be a state-of-the-art Danieli MIDA facility.



All investment and modernisation projects above are scheduled for commissioning in year 2025. Capacity data is in thousand tonnes (kt).

Metals Consulting International (MCI) holds a database of 1,345 steel industry modernisation projects. This database contains individual modernisation records identifying the country, investor, facility, capacity impact, capital cost, capex cost per tonne, commissioning date etc. Please email info@steelonthenet.com or call +44 775 149 0885 for further information.






performance improvement

STEEL PLANT OPERATIONS

Looking to improve your plant's operating performance? We have technical experts in melting casting and rolling, who are able to diagnose problems and offer recommendations. See our case studies page.

Read Our Performance Case Study →